    Must of been a friday, when this track was ballasted?sign1

    Attached Files:

  2. MasonJar

    MasonJar It's not rocket surgery

    Joined:
    Oct 31, 2002
    Messages:
    5,718
    Likes Received:
    0
    If they haven't tamped it yet, or if it will settle more, then it is probably the right amount! ;)

    On some of the tracks near my old house, the ballast came right up to the railhead between the tracks and outside!

    Andrew
  3. jim currie

    jim currie Active Member

    Joined:
    Jun 29, 2003
    Messages:
    1,441
    Likes Received:
    0
    maybe the tamper broke down :D
  4. TruckLover

    TruckLover Mack CH613 & 53' Trailer

    Joined:
    Apr 15, 2006
    Messages:
    4,352
    Likes Received:
    0
    I think it just depends on what the track is serving. If that track is serving a gravel pit then it is good becase of all the overflow from the hoppers and trucks driving around. Also if it is a coal mine (well it would pretty much have to be black), lumber yard or any other major industry were cars and trucks drive over them on a regular basis.
  5. RobertInOntario

    RobertInOntario Active Member

    Joined:
    Mar 23, 2006
    Messages:
    1,409
    Likes Received:
    0
    In my early ballasting attempts, I sort of did the same thing on my layout, and I'm still trying to clean up the excess! :)